Slovenia: SENG launches first...

Slovenian renewable energy company Soske Elektrarne Nova Gorica (SENG) has begun the initial...

Romania: Court suspends environmental...

The Cluj-Napoca Court of Appeal has issued a temporary suspension of the environmental...

Romania: Senate clears way...

The Romanian Senate has approved a new legislative measure allowing construction to begin...

Greece plans capacity market...

The Greek Government is considering the introduction of a capacity market aimed at...
Supported byClarion Energy
HomeSEE Energy NewsGreece: PPC adds...

Greece: PPC adds third turbine to HERON 1 mobile plant to secure Crete’s summer power supply

To meet Crete’s electricity demand during the high-consumption summer season, the Greek Public Power Corporation (PPC) is finalizing the installation of a third turbine unit at the HERON 1 mobile gas-fired power plant. This expansion completes a key energy strategy designed to strengthen the island’s electricity supply.

HERON 1, leased for two years from GEK TERNA, will have a total capacity of 147 MW once all three turbines are operational. The first two units are already producing electricity, and the third turbine is being added in time for the upcoming seasonal increase in power needs.

This temporary power plant serves as an essential interim solution until the permanent Athens-Crete electricity interconnection is fully operational. That infrastructure project is currently in its trial phase, with commercial operation expected by early 2026. The urgency for a reliable power source increased after PPC’s 55 MW plant in Atherinolakkos, southeastern Crete, was taken offline in March due to an explosion.

The HERON 1 lease agreement includes an option for PPC to purchase the facility, allowing flexibility to make the plant a permanent asset if necessary. As with other temporary island power solutions pending grid interconnection, operating costs—both fixed and variable—are covered by Greece’s Public Service Compensation (YKO) mechanism, with the Energy Transition Fund providing additional support if needed.

The addition of the third turbine at HERON 1 reflects PPC’s proactive approach to maintaining grid stability and securing a reliable electricity supply for Crete during its busiest months.

Supported byOwner's Engineer banner

Recent News

Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Slovenia: SENG launches first phase of Kanalski Vrh solar power plant

Slovenian renewable energy company Soske Elektrarne Nova Gorica (SENG) has begun the initial phase of its new solar power plant in Kanalski Vrh. This first stage adds 2.9 MW of installed capacity, marking an important milestone in Slovenia’s ongoing...

Romania: Court suspends environmental permit for nearly completed Rastolița hydropower power plant

The Cluj-Napoca Court of Appeal has issued a temporary suspension of the environmental approval for Hidroelectrica’s Rastolița hydropower project, despite the facility being over 90% complete and scheduled to begin operations in November. The ruling is not yet final...

Romania: Senate clears way for Tarnita-Lăpuștești pumped-storage hydropower plant

The Romanian Senate has approved a new legislative measure allowing construction to begin on the long-delayed Tarnita-Lăpuștești pumped-storage hydropower plant without the need for a new feasibility study. This decision is expected to break years of bureaucratic deadlock and...
Supported byVirtu Energy
error: Content is protected !!