Slovenia: Šoštanj thermal power...

At the end of September, the Šoštanj thermal power plant began an extensive...

North Macedonia: EVN Group...

In the first half of 2025, EVN Group’s electricity distribution arm, Elektrodistribucija, completed...

EU gas phase-out puts...

The European Union’s plan to end Russian gas imports by 2027 presents Greece...

Bulgaria: Black Sea gas...

A new analysis by EY, commissioned by OMV Petrom and NewMed Energy, suggests...
Supported byClarion Energy
HomeSEE Energy NewsGreece: PPC adds...

Greece: PPC adds third turbine to HERON 1 mobile plant to secure Crete’s summer power supply

To meet Crete’s electricity demand during the high-consumption summer season, the Greek Public Power Corporation (PPC) is finalizing the installation of a third turbine unit at the HERON 1 mobile gas-fired power plant. This expansion completes a key energy strategy designed to strengthen the island’s electricity supply.

HERON 1, leased for two years from GEK TERNA, will have a total capacity of 147 MW once all three turbines are operational. The first two units are already producing electricity, and the third turbine is being added in time for the upcoming seasonal increase in power needs.

This temporary power plant serves as an essential interim solution until the permanent Athens-Crete electricity interconnection is fully operational. That infrastructure project is currently in its trial phase, with commercial operation expected by early 2026. The urgency for a reliable power source increased after PPC’s 55 MW plant in Atherinolakkos, southeastern Crete, was taken offline in March due to an explosion.

The HERON 1 lease agreement includes an option for PPC to purchase the facility, allowing flexibility to make the plant a permanent asset if necessary. As with other temporary island power solutions pending grid interconnection, operating costs—both fixed and variable—are covered by Greece’s Public Service Compensation (YKO) mechanism, with the Energy Transition Fund providing additional support if needed.

The addition of the third turbine at HERON 1 reflects PPC’s proactive approach to maintaining grid stability and securing a reliable electricity supply for Crete during its busiest months.

Supported byOwner's Engineer banner

Recent News

Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Slovenia: Šoštanj thermal power plant launches €7.4 million overhaul of first gas turbine

At the end of September, the Šoštanj thermal power plant began an extensive replacement of key components in its first gas turbine, a complex maintenance operation expected to be completed by the end of this month. Once the work...

North Macedonia: EVN Group invests €10.4 million in upgrading electricity network

In the first half of 2025, EVN Group’s electricity distribution arm, Elektrodistribucija, completed a series of major infrastructure projects to modernize and strengthen North Macedonia’s low-voltage electricity network. The initiative aimed to improve network reliability, reduce transmission losses, and...

MOL refinery fire under control as Hungary assesses impact on fuel supply

Hungarian oil and gas company MOL announced that it has started restarting unaffected units at its Danube refinery after a major overnight fire. Fire crews remain on-site as safety inspections continue. The company confirmed that the fire is now...
Supported byVirtu Energy
error: Content is protected !!