Gastrade has announced a new operational milestone for the Alexandroupoli LNG terminal, with its maximum daily regasification capacity increasing to 136.2 GWh as of October 21. This marks a significant rise from the 90.8 GWh per day recorded in mid-September.
The terminal resumed full operations in August following a seven-month shutdown caused by a technical failure that damaged the booster pumps on the Floating Storage and Regasification Unit (FSRU). During the initial restart phase, regasification was limited to 45.4 GWh per day for about a month while safety and performance testing took place.
The gradual restoration of full capacity was completed as scheduled at the start of the new gas year on October 1, 2025.
With this latest upgrade, the Alexandroupoli facility has achieved its highest throughput since beginning operations in October 2024, further reinforcing its position as a critical energy hub for southeastern Europe.