Bosnia and Herzegovina: Ivovik wind farm enters final phase

Despite facing numerous challenges, including difficult terrain and rising material costs, the Ivovik wind farm project in Bosnia and Herzegovina (BiH) has entered its final phase and is poised to make a significant contribution to the country’s renewable energy supply.

After receiving the operational permit, the first turbines of the wind farm have begun generating electricity. A trial operation is currently underway, marking an essential step in the process of commissioning the wind farm. During this trial period, each turbine will go through a phased startup process, with detailed performance evaluations to ensure the full integration of the wind farm into the national electricity grid.

Located near the cities of Livno and Tomislavgrad, the Ivovik wind farm will add 84 MW to Bosnia’s renewable energy portfolio. The project is ambitiously expected to provide clean electricity to 100,000 households. With an annual production goal of 259 GWh, it will remain the largest wind energy project in BiH.

The wind farm will consist of 20 turbines, each with a capacity of 4.2 MW, totaling 84 MW. The project is estimated to cost around 68 million euros. In September 2022, following the approval by the Herzeg-Bosnia Canton Government for Sinohydro Holding, a subsidiary of Chinese Powerchina Resources, to sell its 51% stake in the company overseeing the construction and operation of the Ivovik wind farm, the share was acquired by Luxembourg-based Ivovik Wind Power.

The current capital structure of the project company, VE Ivovik, is as follows: Chinese CNTIC Capital Co. holds a 39% stake, while Ivovik Wind Power owns 61%.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Bosnia and Herzegovina drafts KfW loan for 132 MW Poklečani wind farm

KfW financing draft for Poklečani wind farm Bosnia and Herzegovina has approved a draft financing agreement with German development bank KfW for the 132 MW Poklečani wind farm. The project is described as one of the largest planned renewable-energy investments...

FBiH tenders 1.67 million litres of strategic diesel for Blažuj terminal

Procurement details for strategic diesel stocks The Federation of Bosnia and Herzegovina has launched a procurement for 1.67 million litres of diesel to expand strategic fuel stocks at the Blažuj petroleum terminal near Sarajevo. The contract is valued at approximately...

Bosnia advances €103 million financing for Poklečani wind and Elektrokrajina grid upgrades

Bosnia and Herzegovina has advanced around €103 million of proposed financing covering new wind capacity and distribution-grid upgrades. The package targets both additional generation and constraints in the network that increasingly limit renewable deployment. The Council of Ministers has...
Supported byVirtu Energy