In November 2025, the Krsko nuclear power plant, jointly owned by Slovenia and Croatia, generated 504,486 MWh of net electricity, surpassing the planned output of 495,000 MWh by 1.92%.
For comparison, in November 2024, the plant produced 504,839 MWh, exceeding the target of 493,000 MWh by 2.4%. Throughout this period, NPP Krsko operated fully within technical specifications, with all safety systems fully functional.
Both the availability factor and the capacity factor stood at 100%, and no technical issues were reported, confirming the plant’s consistent performance and operational reliability.