In September 2025, the Krsko nuclear power plant, jointly owned by Slovenia and Croatia, generated 449,426 MWh of net electricity, slightly exceeding the planned output of 446,000 MWh by 0.77%.
On 28 September, NPP Krsko completed its 34th fuel cycle and began a scheduled overhaul. During this cycle, the plant produced a total of 8,514.5 GWh of electricity. In comparison, in September of the previous year, the plant generated 496,008 MWh of net electricity, 0.6% above the planned 493,000 MWh.
The plant operated within all technical specifications, with all safety systems fully functional. Both the availability and capacity factors reached 100%, and no technical issues were reported during the period.