Montenegro: BSD Mont plans...

Montenegrin company BSD Mont has announced plans to build an 84 MW hybrid...

North Macedonia: Energy consumption...

In October 2024, North Macedonia's total electricity consumption reached 450,997 MWh, with natural...

Greece: ADMIE completes Athens-Crete...

Greek electricity transmission system operator ADMIE has completed the development of the Athens-Crete...

Bosnia and Herzegovina: Severe...

According to Bosnia's state-owned power utility, ERS, several power outages have affected over...
Supported byClarion Energy banner
HomeSEE Energy NewsSerbia: Trans-Balkan corridor...

Serbia: Trans-Balkan corridor project – contract for transformer stations signed

Serbian electricity transmission system operator EMS signed a project with local consortium consisting of Energotehnika Juzna Backa, Elektromontaza Kraljevo and Elnos BL. The 6.5-million-euro contract is for works on transformer stations within the second phase of the Trans-Balkan Electricity Corridor project.

The works include the construction of a 400 kV switchyard and 400/220 kV transformer in Kraljevo 3 substation, and equipping a 400kV feeder bay in the 400/110 kV Kragujevac 2 substation. The works are expected to be completed within 610 days.

The works are a part of the second phase of Trans-Balkan Electricity Corridor project, along with the construction of a 60 kilometers-long 400 kV transmission line between Kragujevac and Kraljevo. 13.5 million euros worth contract for the line was signed in March with Kodar Energomontaza and the works on the line started in June. The construction is expected to be completed in early 2021.

Total investment in the second phase of the project amounts to 29.6 million euros, which will be funded by 15 million euros loan from German KfW Bank, 6.5 million euros grant for the European Union and EMS’ own resources. The first phase of the Trans-Balkan project in Serbia included the construction of a double-circuit 400 kV transmission line from Pancevo to Romanian border, which was completed in December 2017 and was entirely financed by EMS. The third phase envisages the construction of a 109 kilometers-long 400 kV transmission line from Bajina Basta to Obrenovac, the upgrade of Bajina Basta substation’s capacity to 400 kV, and the overhaul of the Obrenovac substation. The fourth phase will include the construction of 400 kV transmission line linking Bajina Basta to Bosnia and Herzegovina and Montenegro. The entire Trans-Balkan Electricity Corridor, linking Montenegro, Bosnia and Herzegovina, Serbia and Romania via a 400 kV transmission line and Montenegro and Italy via an undersea cable, is expected to be operational in 2022.

 

 

 

Supported byOwner's Engineer banner

Recent News

Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Montenegro: BSD Mont plans 84 MW hybrid power plant in Rožaje municipality

Montenegrin company BSD Mont has announced plans to build an 84 MW hybrid power plant in the northeastern municipality of Rožaje. The Montenegrin Government has granted approval for the preparation of the necessary technical documentation for the project. The Cosovica...

North Macedonia: Energy consumption and production in October

In October 2024, North Macedonia's total electricity consumption reached 450,997 MWh, with natural gas usage amounting to 17.69 million cubic meters, coal consumption at 246,735 tons, and petroleum products consumption at 103,513 tons, according to data from the State...

Greece: ADMIE completes Athens-Crete electricity interconnection

Greek electricity transmission system operator ADMIE has completed the development of the Athens-Crete electricity interconnection, a €1.1 billion project. The company has announced that preliminary testing and equipment pre-commissioning have begun, with trial operations expected to follow soon. The testing...
Supported bySEE Mining News
error: Content is protected !!