Europe: Gas prices slide...

In Week 30 of 2025, European gas prices declined, with Dutch TTF prices...

Region: Heatwave drives SEE...

In Week 30 of 2025, electricity market prices rose significantly across most Southeast...

Romania: INVL Renewable Energy...

INVL Renewable Energy Fund I, managed by INVL Asset Management and focused on...

Croatia: Summary of Guarantees...

On 29 July, a total of 231,827 Guarantees of Origin (GOs) were sold...
Supported byClarion Energy
HomeNews Serbia EnergySerbia, Does EPS...

Serbia, Does EPS pollute the Sava River?

While the State Audit Institution claims that the Electric Power Company of Serbia releases waste water into the Sava River without treatment, the company emphasizes that its quality is monitored regularly, and the expert public emphasizes that the authorities can and should easily determine who is telling the truth in this matter.

The public company Elektroprivreda Srbije (EPS) did not build a wastewater treatment plant “Termoelektrana Nikola Tesla B” (TENT B), so the wastewater is discharged into the Sava without treatment and is a risk to the environment, the State Audit Institution (DRI) warned recently.

The state auditors stated in the report on the feasibility audit of the “Management of Industrial Wastewater” that EPS, i.e. “TENT A” and “TENT B”, did not continuously examine the quality parameters of waste water and their impact on the environment.

It was pointed out that “TENT A” did not replace the old technology of hydraulic transport of “rare” suspension of ash and water, with technology that would reduce water pollution.

The biggest polluters are industrial and communal waste water that is discharged directly into waterways without prior treatment, and where industrial water can be particularly dangerous due to the toxic substances they contain – said the president of DRI DuÅ¡ko Pejović at the presentation of the report.

In response to the report of the State Audit Institution on waste water treatment, EPS announced that the quality of surface and underground water in the vicinity of the “Nikola Tesla B” Thermal Power Plant has been monitored regularly since 1983.

Control of the quality of waste water in TENT B and its impact on water receivers and groundwater is done four times a year, except for the return cooling water, which is analyzed once a month.

All these tests are carried out by legal entities authorized by the competent ministry and they independently sample the waste water at the outlet, take the sample to the laboratory for examination of the legally prescribed parameters, after which they issue a report.

All analyzes indicate that the operation of TENT B does not affect the quality of the Sava River and that the quality of the river upstream and downstream of the thermal power plant is in a good ecological status, according to the EPS announcement.

Officials in that company point out that the published SAI report did not state that this conclusion refers to the only case that waste water testing was not performed three times due to difficulties with the public procurement procedure, which was announced within the legal deadline.

– Elektroprivreda Srbije is not the largest generator of industrial wastewater in the Republic of Serbia, and the public should know that it is primarily cooling wastewater that is used in a closed pipe system without the use of any chemicals, that is, it does not belong to chemical-technological wastewater. All of this is confirmed in the “Environmental Impact Assessment Study of the found condition at the location of the Nikola Tesla B TPP from September 2022, which was carried out by “Energoprojekt Entel”. In that study, it is stated that the analysis of the examined parameters in samples of the Sava before and after the inflow of waste water does not indicate a significant impact of waste water on the quality of the Sava River and that the examined water course of the Sava belongs to a good ecological status (class II) – they claim in the EPS, adding that based on the results obtained.

In EPS, they say that every year in January they submit reports on waste water testing to the competent state bodies, more precisely to the Environmental Protection Agency, the Ministry of Environmental Protection, the Public Water Company Srbijavode, and the Water Directorate of the Ministry of Agriculture, Forestry and Water Management.

– The SAI report does not mention that according to Article 98 of the Law on Water, the deadline for the wastewater treatment plant in TENT B to start operating is December 31, 2025. We would like to point out that EPS initiated the project, which is currently in the stage of drafting the project documentation, the planned budget is 10.5 million euros from JP EPS’s own funds, and during February a request for a construction permit will be submitted – concludes EPS.

Sign up for updates & special reports

Supported byOwner's Engineer banner

Recent News

Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Serbia plans to more than double gas imports from Azerbaijan to 1 billion cubic meters annually

The Serbian Energy Ministry has announced intentions to increase annual gas imports from Azerbaijan to 1 billion cubic meters, a rise of over 2.5 times the current agreement of 400 million cubic meters. Negotiations for new supply contracts are expected...

Serbia: US Treasury extends sanctions delay on NIS for fifth time

The US Treasury Department has postponed the activation of sanctions on Serbian oil company NIS for an additional 30 days, marking the fifth extension since January. Serbian Energy Minister Dubravka Djedović noted that securing a further, longer reprieve is currently...

Serbia: Government eyes takeover of delayed Plandište wind project to boost renewable goals

The Serbian Government has expressed interest in taking over the Plandište wind power project, currently jointly owned by Serbian oil company NIS and Swiss-based MET Renewables. The news surfaced after a recent NIS Board of Directors meeting, during which...