Slovenia: SENG launches first...

Slovenian renewable energy company Soske Elektrarne Nova Gorica (SENG) has begun the initial...

Romania: Court suspends environmental...

The Cluj-Napoca Court of Appeal has issued a temporary suspension of the environmental...

Romania: Senate clears way...

The Romanian Senate has approved a new legislative measure allowing construction to begin...

Greece plans capacity market...

The Greek Government is considering the introduction of a capacity market aimed at...
Supported byClarion Energy
HomeSEE Energy NewsRomania: Transelectrica’s investment...

Romania: Transelectrica’s investment plan approved

Electricity transmission system operator Transelectrica’s electricity network development plan was approved by the National Regulatory Authority for Energy (ANRE) until 2029.

Investments worth 1.18 billion euros are planned for upgrading existing electricity transmission networks, for integrating production from renewable sources and other production capacities, for increasing interconnection capacity, for security of supply, as well as for development of IT systems, smart metering, telecommunications systems and critical infrastructure. According to ANRE, over 60 million euros will come from non-reimbursable European funds.

During the period 2023-2024, the construction of Cernavoda–Staple and Smarten–Guianas transmission lines are planned, which will provide the evacuation of the electricity produced from renewable sources in the Dobrogea area to the central, western and northern consumption centers of the country. In addition, in order to increase the security of supply of electricity to the Bucharest metropolitan area, investment works to complete the necessary lines and power stations will be completed in 2024-2029, so as to increase safety and reliability in this area. The development plan will integrate projects of common interest which contribute to the implementation of the European Union’s strategic priorities for trans-European energy infrastructure: So-called Black Sea Corridor and Mid-Continental East Corridor, with estimated commissioning times between 2025 and 2027 and interconnection projects aiming at reaching the 15 % interconnection target set at European Commission level by 2030.

In 2020, this indicator has increased to 11 % compared to 7 % in 2017, which is due to the updating of the installed capacity in the national electricity system taking into consideration only the licensed for commercial exploitation groups (as required by ANRE), but also due to the increasing the NTC values on the Bulgarian border from 250-300 MW to 900 MW.

 

 

 

Supported byOwner's Engineer banner

Recent News

Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Slovenia: SENG launches first phase of Kanalski Vrh solar power plant

Slovenian renewable energy company Soske Elektrarne Nova Gorica (SENG) has begun the initial phase of its new solar power plant in Kanalski Vrh. This first stage adds 2.9 MW of installed capacity, marking an important milestone in Slovenia’s ongoing...

Romania: Court suspends environmental permit for nearly completed Rastolița hydropower power plant

The Cluj-Napoca Court of Appeal has issued a temporary suspension of the environmental approval for Hidroelectrica’s Rastolița hydropower project, despite the facility being over 90% complete and scheduled to begin operations in November. The ruling is not yet final...

Romania: Senate clears way for Tarnita-Lăpuștești pumped-storage hydropower plant

The Romanian Senate has approved a new legislative measure allowing construction to begin on the long-delayed Tarnita-Lăpuștești pumped-storage hydropower plant without the need for a new feasibility study. This decision is expected to break years of bureaucratic deadlock and...
Supported byVirtu Energy
error: Content is protected !!