Montenegro: EPCG confirms TPP...

Montenegro’s state-owned power utility EPCG has issued a statement refuting media reports that...

Greece: DESFA launches tender...

The Greek natural gas transmission system operator DESFA has announced a tender worth...

Bulgaria: BICA warns new...

The Bulgarian Industrial Capital Association (BICA) has expressed concerns about the government’s new...

Romania: GE Vernova secures...

GE Vernova has signed an agreement with Greenvolt International Power to supply wind...
Supported byClarion Energy
HomeSEE Energy NewsMontenegro to import...

Montenegro to import 160 million euros worth of electricity in 2025

 

The Pljevlja thermal power plant will be shut down for several months in 2025 due to ecological reconstruction, which will force Montenegro to import large amounts of electricity, worth an estimated EUR 160 million, according to the energy and mining minister, Saša Mujović.

Power utility Elektroprivreda Crne Gore (EPCG), the operator of TPP Pljevlja, has started the ecological reconstruction to modernize the facility, align it with European emissions standards, and extend its lifespan. However, given that the 225 MW plant accounts for 40% of the country’s electricity production, its shutdown will require substantial imports.

EPCG officially launched the reconstruction project in April 2022, when it was announced it should last about two and a half years.

Now, during an air pollution panel discussion in the northern city of Bijelo Polje, minister Saša Mujović said that EPCG had not yet procured electricity for 2025, when the TPP Pljevlja would be reconstructed, Vijesti reported.

Mujović stressed that the proposal to subsidize electricity bills for residents of Bijelo Polje was unsustainable. He is almost certain that similar subsidies will be canceled next year for Pljevlja as well, which is considered by far the most polluted city in the country because of TPP Pljevlja and coal mining.

According to him, subsidies for Bijelo Polje for 2024 and 2025 are even more unsustainable with the planned shutdown of TPP Pljevlja, when Montenegro will be forced to import electricity.

About EUR 160 million will be spent on the imports, instead of making an income in the similar amount, which is a heavy burden for a poor country such as Montenegro, Mujović pointed out.

He says the fact that Montenegro has not yet secured electricity for 2025 makes him restless, adding that he will act on the issue very soon.

In 2023, EPCG posted an EUR 80 million profit. Montenegro usually generates enough electricity for its domestic consumption, and often exports surpluses. Sales abroad depend on the water levels, considering that more than 50% of electricity is generated in hydropower plants. In recent years, the country has exported several percent of its output.

Source: Balkan Green Energy News

Supported byOwner's Engineer banner

Recent News

Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Serbia: EU Carbon Border Tax poses major challenge for power sector and energy transition

From 2026, Serbia will fall under the EU’s Carbon Border Adjustment Mechanism (CBAM), which imposes additional costs on carbon-intensive exports to the Union. According to the Fiscal Council, the state-owned power utility EPS, which supplies most of the country’s...

Montenegro: EPCG confirms TPP Pljevlja reconstruction on schedule and within budget

Montenegro’s state-owned power utility EPCG has issued a statement refuting media reports that questioned the progress of the ecological reconstruction of the Pljevlja thermal power plant. The company emphasized that the project is advancing as planned and remains fully...

Greece: DESFA launches tender for pipeline linking Alexandroupoli gas plant to national network

The Greek natural gas transmission system operator DESFA has announced a tender worth 1.22 million euros for the supply of steel pipes needed to construct a new pipeline that will connect the planned Alexandroupoli gas-fired power plant to the...
Supported byVirtu Energy
error: Content is protected !!